Week |
Topic(s) |
Text |
Lab |
Homework |
|
1 |
Scope of Class Review of Important Concepts from Fluid Mechanics |
Ch 1, 2-4 |
Instrument calibration Flow-measuring devices (hydraulics lab) |
Prob 4.5.3 |
|
I. Pipe Flow |
||||
|
2 |
Multiple & Branching Pipelines Pipe Networks |
4.5, 12.4, 12.6 |
Flow in a parallel pipe network I (hydraulics lab) |
4.5.4, 4.5.7, 12.4.1 due Friday |
|
3 |
Pumps and pump curves Parallel and Series demo |
12.2 |
Flow in a parallel pipe network II (hydraulics lab) |
12.6.4 (solve for PVC pipe and for cast iron pipe), 12.5.1 |
|
4 |
Water distribution systems Movie Day (Brandes at Conf) |
12.3 |
NO LAB - WORK ON PROJECT AND PROGRESS REPORT | see Handouts page |
|
II. Open Channel Flow |
||||
|
5 |
Uniform Open Channel Flow Best Hydraulic Section, Channel Design |
5.1, 15.2, 15.3 |
Open Channel I - Weirs (hydraulics lab) |
No HW, Exam Week |
|
Wed, Feb 25, Evening Exam 1; progress report on project due |
||||
|
6 |
Open Channel Flow Specific energy, critical flow |
5.2, 5.3, 5.4 |
Open Channel II - Orifices (hydraulics lab) |
5.1.2, 5.1.3, 5.1.5 due Fri |
|
7 |
Open Channel Flow Weirs, flow transitions |
5.6 |
Cadillac Desert I (hydraulics lab) |
See handouts page |
|
Spring Break! March 16 - 20 |
||||
|
III. Hydrology and Stormwater Management |
||||
|
8 |
Standard Step Method Prob & Stats in Hydrol & Water Resources |
Ch 10 |
Streamflow Measurement and Rating Curves (field) |
5.5.1, 5.5.2 and see Handouts page - due Fri |
|
9 |
Frequency Analysis and Return Period Moles Trip, Friday, April 3 |
Ch 10 |
Analysis of historic Del River Floods (computer lab) |
dunno |
|
10 |
Watersheds & hydrologic processes Role of groundwater |
Ch 7 |
Watershed delineation (computer) | dunno |
|
Wed, April 8, Evening Exam 2; Progress report and detailed outline of paper with background section due |
||||
|
11 |
Precipitation and design storms Stormwater runoff |
8 |
GW Flow Direction | |
|
12 |
Stormwater Runoff |
8 |
No Lab - Project Time | |
|
13 |
Stormwater Routing |
9, 15.4 |
WinTR-55 Runoff Model and Routing (computer) |
|
|
14 |
Floods and Flood Control |
Ch 14 |
Movie Time | None! |
|
Finals Week, Exam 3 |
||||